|
Mon-Fayette Transportation Project
- Sections 52D & 52F2
Harrisburg, PA
DMJM+HARRIS has completed preliminary engineering for
a new eight-kilometer (five-mile) segment of the Mon-Fayette
Expressway Project in Washington County, PA. Additionally,
DMJM+HARRIS is completing final design plans for 3.7
kilometers (2.3 miles) of this new four lane divided
roadway. Key features of this project include a diamond
interchange with ramp toll plazas and interchange lighting
and the design of eight new structures, which range
in length from 51 to 396 meters (170 to 1300 feet) and
in height from 15 to 34 meters (50 to 110 feet)
Among these structures are two twin mainline bridges
crossing streams and local roads. The first structure
is a seven-span continuous welded, steel plate girder
with a length of 396 meters (1300 feet). The other is
a 274 meter (900 feet) curved steel plate girder consisting
of five continuous spans. Superstructure design for
both bridges was performed using BSDI, a three-dimensional
finite element software package. Single column flared
concrete piers comprise the substructure of these long
span bridges. The piers were designed with additional
seat width to accommodate an extra girder line for future
deck replacement or possible widening. The foundation
design incorporated the use of soil grouting measures
to stabilize the numerous mine shafts in the vicinity
of the structures.
In addition to the bridge structures required by the
new alignment, DMJM+HARRIS engineers also designed
two cast-in-place box culverts. A 28-meter (90-foot)
culvert will employ staged construction methods and
a temporary stream diversion while the 171-meter (560-foot)
culvert will support the mainline and 19 meters (62
feet) of fill.
The roadway design has been complicated by the need
to negotiate a myriad of issues with the owner of a
coal refuse storage site along the proposed alignment.
DMJM+HARRIS has been instrumental in these negotiations.
By careful consideration of the needs of both the Pennsylvania
Turnpike Commission and the mine, DMJM+HARRIS has created
a plan that optimizes the requirements of both parties.
Examples of this include allowing the mine operations
to place coal refuse against the expressway embankment
slopes thereby expanding the mines storage capacity;
placing a dam, which separates the expressway from the
mines slurry pond, at a location that maximizes
the ponds capacity and hence minimizes the amount
of compensation due the mines owner; and redesign
of the environmental impact statement for mine access
roads concepts which reduced the project cost by approximately
$6,000,000 and also allows for future recreational use
of the refuse site after it is capped and reclaimed.
Other aspects of the project include the design of
eight storm water retention basins to minimize impacts
to the existing water shed, final right-of-way acquisition
plans involving 35 property owners, approximately 98
hectares (246 acres), and both surface and subsurface
coal rights, and erosion and sedimentation control plans.
|