|
George P. Coleman Bridge Replacement
Georgetown, Virginia
Tidewater Construction Corporation (TCC) was retained
by the Virginia Department of Transportation (VDOT)
to replace the two-lane George P. Coleman Bridge and
its approaches with new structures accommodating four
lanes. With an overall length of 2,540 feet, the bridge
had six main steel struss spans; the longest 560 feet
long and weighing 4,000 tons. Two of the spans were
designed as swing sections, allowing the bridge to open
for the passage of tall ships.
TCC elected to construct the new spans on temporary
piers over water in a fabrication yard 30 miles from
the old bridge. Each completed span was lifted from
its fabrication piers using towers mounted on two barges
placed under the span. The barges could then transport
the bridge to the permanent site, where each span was
dropped onto the piers by adding ballast to the barges.
This approach enabled TCC to complete the installation
in a mere nine days, earning the VDOTs gratitude
(and a substantial bonus). But the solution created
complex engineering issues of its own. DMJM+HARRIS solved
those issues by conducting myriad calculations of load
stresses, shear forces, chord deformations, and structural
requirements. Since most hydrodynamic analysis tools
were not designed to consider the interaction among
two barges and an interconnecting span, DMJM+HARRIS
developed its own analysis approach, using pre-and post-processors
to generate, organize, and dissect the load requirements.
After meticulously modeling each bridge span, the barges,
and the towers, we designed load equalizer systems that
would make the system work, reducing the support steel
required by 110 tons in the process. Our work was so
successful that TCC expanded Harris's scope to include
final design of the entire support system and necessary
bridge strengthening.
|